Carter’s Green Medical Centre

Completed building handed over!

We are delighted to have successfully completed and handed over the new building.

April 2021


Building nearing completion

With the scaffolding down, and works inside coming to an end soon, the building is rapidly approaching completion.

March 2021


External walls are nearing completion

Carter’s Green Medical Centre is progressing well, with the external walls almost finished.

August 2020


Steelwork of new building’s superstructure almost complete

Steelworks are nearing completion at Carter’s Green Medical Centre, and the building’s shape and volume is already apparent.

February 2020


Start of the new building’s superstructure

Erection of the steelwork begins at Carter’s Green Medical Centre:

January 29 2020


Progress in the new year at Carter’s Green Medical Centre.

Foundations have now been poured, ready for the erection of the steelwork.

Foundations have now been poured.

January 17 2020


Progress on site before Christmas

Foundations and piling work are underway on site.

Carter’s Green Medical Centre
Carter’s Green Medical Centre
Piling works underway at the new Carter’s Green Medical Centre

November 6 2019


Awarded the project for the Carter’s Green Medical Centre

We are delighted to confirm that we have been awarded the project for the Carter’s Green Medical Centre, on the site of the existing Sandwell General Hospital.

The new centre will provide 1800 square metres of much needed Healthcare facilities over 3 floors.

October 7 2019